Interference with Traffic Update - Wednesday October 24, 2018 @ 2:30 p.m.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Thursday 10/25/18. Construction on the below mentioned roadways will start at 7:30am to 5:30pm for the purpose of installing new sewer line.

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 


 

Interference with Traffic Update - Tuesday October 23, 2018 @ 1:30 p.m.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Wednesday 10/24/18. Construction on the below mentioned roadways will start at 7:30am to 5:30pm for the purpose of installing new sewer line.

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 


Interference with Traffic Update - Monday October 22, 2018 @ 3:00 p.m.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Tuesday 10/23/18. Construction on the below mentioned roadways will start at 7:30am to 5:30pm for the purpose of installing new sewer line.

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update - Monday October 22, 2018 @ 8:00 a.m.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Monday 10/22/18. Construction on the below mentioned roadways will start at 7:30am to 5:30pm for the purpose of installing new sewer line.

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update - Friday October 19, 2018 @ 8:00 a.m.

 

On Friday, October 19, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Friday 10/19/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Wednesday October 17, 2018 @ 9:00 a.m.

 

On Thursday, October 18, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Thursday 10/18/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Tuesday October 16, 2018 @ 3:30 p.m.

 

 On Wednesday, October 17, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston):

 

Pipe Plus Inc. will be working in the roadways listed below Wednesday 10/17/18. Construction on the below mentioned roadways will start at 7:30am to 5:30pm for the purpose of installing new sewer line.

 

 1. Callie Road – will have one lane of alternating traffic near the 1400 block of Callie Road.

 

 2. Brittany Woods – will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

 3. Woodcliff Drive – will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Monday October 15, 2018 @ 2:30 p.m.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston):

 

On Tuesday, October 16, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Pipe Plus Inc. will be working in the roadways listed below Tuesday 10/16/18. Construction on the below mentioned roadways will start at 7:30am to 5:30pm for the purpose of installing new sewer line.

 

 1. Callie Road – will have one lane of alternating traffic near the 1400 block of Callie Road.

 

 2. Brittany Woods – will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

 3. Woodcliff Drive – will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Monday October 15, 2018 @ 9:30 a.m.

 

Due to inclement weather, work is canceled on Porters today 10/15/18

 


 

Interference with Traffic Update –Friday October 12, 2018 @ 8:15 a.m.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston):

 

Pipe Plus Inc. will be working in the roadways listed below Friday 10/12/18. Construction on the below mentioned roadways will start at 7:30am to 5:30pm for the purpose of installing new sewer line.

 

 1. Callie Road – will have one lane of alternating traffic near the 1400 block of Callie Road.

 

 2. Brittany Woods – will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

 3. Woodcliff Drive – will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Thursday October 11, 2018 @ 9:30 a.m.

 

Due to inclement weather, work is canceled on Porters today.

 


Interference with Traffic Update –Tuesday October 9, 2018 @ 1:00 p.m.

 

On Wednesday, October 10, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Wednesday 10/10/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Monday October 8, 2018 @ 12:30 p.m.

 

On Tuesday, October 9, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Tuesday 10/09/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Friday October 5, 2018 @ 9:30 a.m.

 

On Monday, October 8, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Monday 10/08/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Wednesday October 3, 2018 @ 3:00 p.m.

 

On Thursday, October 4, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Thursday 10/04/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Tuesday October 2, 2018 @ 1:30 p.m.

 

On Wednesday, October 3, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Wednesday 10/03/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Monday October 1, 2018 @ 1:00 p.m.

 

On Tuesday, October 2, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Tuesday 10/02/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Friday, September 28, 2018 @ 8:45 a.m.

 

On Monday, October 1, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Monday 10/01/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update –Thursday, September 27, 2018 @ 2:45 p.m.

 

On Friday, September 28, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Friday 09/28/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only. 

 


Interference with Traffic Update –Wednesday, September 26, 2018 @ 4:30 p.m.

 

On Thursday, September 27, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Thursday 09/27/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only. 

 

 


Interference with Traffic Update –Wednesday, September 19, 2018 @ 3:00 p.m.

 

On Thursday, September 20, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston): 

 

Pipe Plus Inc. will be working in the roadways listed below Thursday 09/20/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.   

 


Interference with Traffic Update –Tuesday, September 18, 2018 @ 4:00 p.m.

 

On Wednesday, September 19, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston):

 

Pipe Plus Inc. will be working in the roadways listed below Wednesday 09/19/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line.

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update – Monday, September 17, 2018 @ 11:00 a.m.

 

On Tuesday, September 18, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston):   

 

Pipe Plus Inc. will be working in the roadways listed below Tuesday 09/18/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing new sewer line. 

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.   

 


Interference with Traffic Update – Monday, September 17, 2018 @ 10:30 a.m.

 

On Monday, September 17, 2018 construction crews will not be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. Due to inclement weather.

 


Interference with Traffic Update – Friday, September 14, 2018 @ 11:00 a.m.

 

On Monday, September 17, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston):

 

Weather permitting, Pipe Plus Inc. will be working in the roadways listed below Monday 09/17/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing a new sewer line.

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update – Thursday, September 13, 2018 @ 3:30 p.m.

 

On Friday, September 14, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston):

 

Pipe Plus Inc. will be working in the roadways listed below Friday 09/14/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing a new sewer line.

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.

 


Interference with Traffic Update – Wednesday, September 12, 2018 @ 2:30 PM

 

On Thursday, September 13, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston):

 

Pipe Plus Inc. will be working in the roadways listed below Thursday 09/13/18. Construction on the below-mentioned roadways will start at 7:30 AM to 5:30 PM for the purpose of installing a new sewer line

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.   

 


Interference with Traffic Update – Wednesday, September 12, 2018 @ 9:00 AM

 

On Wednesday, September 12, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston):

 

Pipe Plus Inc. will be working in the roadways listed below Wednesday 09/12/18. Construction on the below-mentioned roadways will start at 7:30 AM to 5:30 PM for the purpose of installing a new sewer line

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.   

 


Interference with Traffic Update – Monday, September 10, 2018 @ 1:00 p.m.

 

On Tuesday, September 11, 2018 construction crews will be working on Brittany Woods Road, Callie Road, and Woodcliff Drive. This schedule is subject to change should inclement weather occur.

 

Notice from Pipe Plus, Inc. (Contractor for The Sanitary Board of the City of Charleston):

Pipe Plus Inc. will be working in the roadways listed below Tuesday 09/11/18. Construction on the below-mentioned roadways will start at 7:30 am to 5:30 pm for the purpose of installing a new sewer line.     

 

1. Callie Road - will have one lane of alternating traffic near the 1400 block of Callie Road.

 

2. Brittany Woods - will have one lane of alternating traffic near the 100 block of Brittany Woods.

 

3. Woodcliff Drive - will be closed to thru traffic and open to emergency and local traffic only.   

     

  









Charleston Sanitary Board
208 26th Street W

Charleston, WV 25387

304-348-1084 Administration

304-348-8136 Customer Service

304-348-6876 Sewer Emergencies